Pasco County officials were hoping for a decision on a permit, and a construction start for the proposed Ridge Road extension by winter 2018. Instead, a revised schedule provided to the United States Army Corps of Engineers projects the anticipated permit decision in late February 2019. Despite the revised time frame, Pasco County Administrator Dan Biles remains hopeful of a quicker … [Read more...]

Ridge Road extension is a step closer

Pasco County is placing a future order to buy wetlands adjacent to the Connerton Preserve to offset wetlands that would be lost due to construction of the Ridge Road extension. The Pasco County Commission approved a wetlands credit purchase agreement with Ecosystem Investment Partners Credit Co., for up to $4.4 million at its March 27 meeting in New Port Richey. The item, part of the … [Read more...]