The Laker/Lutz News

Serving Pasco since 1981/Serving Lutz since 1964

  • Home
  • News
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills/East Pasco
    • Business Digest
    • Senior Parks
    • Nature Notes
    • Featured Stories
    • Photos of the Week
    • Reasons To Smile
  • Sports
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills and East Pasco
    • Check This Out
  • Education
  • Pets/Wildlife
  • Health
    • Health Events
    • Health News
  • What’s Happening
  • Sponsored Content
    • Closer Look
  • Homes
  • Obits
  • Public Notices
    • Browse Notices
    • Place Notices

Diverging Diamond is behind schedule

October 27, 2020 By B.C. Manion

A road project that’s expected to reduce congestion at the Interstate 75 and State Road 56 is running behind schedule, and Pasco County commissioners aren’t happy.

Pasco County Commission Chairman Mike Moore raised the issue during the board’s Oct. 20 meeting — citing the apparent lack of workers on the project.

“I drive it daily. My wife drives it daily. My oldest daughter probably drives it three to four times a week,” he said.

Pasco County Commission Chairman Mike Moore is calling on state road officials to apply greater pressure to get the Diverging Diamond project back on track. (File)

“Yesterday, when I drove through there, I took a few photos. I saw one truck. I don’t know what he was doing, I’m not a contractor. And, I saw two guys standing on the side, down below.

“On a project of that magnitude, those are the only people I saw working on it Monday — a sunny Monday.

“That was about 1:15, 1:30 (in the afternoon), when I drove through there. Those were the only people working on that project when I drove by there.

“That’s insane.

“That’s ridiculous.

“That’s embarrassing,” Moore said.

“I know Commissioner (Kathryn) Starkey and I received a letter from a group of businesses over on the west side of the interchange, everywhere from the outlet mall to across the street to Sierra’s properties (Cypress Creek Town Center), too,” Moore said.

“It’s frustrating to all of our constituents here. It’s frustrating to the business owners,” he said.

It’s particularly irritating given the fact that the county worked with local state legislators to get the project moved, and now it’s behind schedule, Moore said.

“Now, we’re going into 2021. This was supposed to be done in the summer of ‘21, and be finished and completed. Unfortunately, they’re delayed.

“We have absolutely zero control, and when I say zero, we have zero control over these contractors for that project because that is a DOT project,” the commission chairman added.

Moore said he expressed the county’s displeasure to David Gwynn, secretary for District 7 of the Florida Department of Transportation.

Gwynn responded with an email outlining what’s happened so far in the project, and the DOT’s actions.

The project was started in early 2019 with an original schedule of 800 days, which would result in a finish date of April 2021, Gwynne’s email notes.

Commissioner Jack Mariano said the county needs to keep the pressure on, to get the state road project finished closer to its original completion date.

That schedule did not account for rain and holiday allowances or other factors outside the contractors control, the email adds.

To date, the contractor has been granted:

  • 99 days for weather
  • 34 days of holiday time
  • 30 days for unforeseen conditions

As a result, 163 days will be added to the contract, bringing the new end date to Aug. 26, 2021, the email notes.

“The department has discussed its concern with the contractor, DAB Constructors, as a result the contractor has gone to a 6-day work week to mitigate the schedule, and has agreed to focus their resources on completing existing work,” the email says.

The DOT also is looking for opportunities to move the job forward, the email notes, including:

  • Approving the use of alternate fill materials less sensitive to water, to accelerate work in low lying areas
  • Examining ways to combine traffic phases to shorten the overall duration of the project
  • Utilizing alternate road base options to accelerate new roadway construction
  • Examining ways to reconfigure walls on the project to shorten construction duration

Gwynn’s email says that “should the contractor not meet the contract end date, liquidated damages, of $9,837 a day, will be assessed for every day that the contractor is late in completing the project.”

The email goes on to say that the department sent a letter of concern to the contractor on March 23, and continues to review the contractor’s progress.

Finally, Gwynn said, “Please be assured that we are doing everything we can to hold the contractor accountable and accelerate the schedule where possible.”

Starkey said “I think DOT is doing as much as it can, to push it along,” but, she would like to see changes in the way contracts are awarded, to put a higher value on a company’s performance.

Moore said he’s happy to see what the DOT is doing, but isn’t satisfied with the results.

“The pressure needs to stay on,” Moore said.

“Basically, what needs to happen, is they need to hold their feet to the fire,” Moore said.

Commissioner Jack Mariano agreed: “Keep the pressure on.”

Published October 28, 2020

Share this:

  • Tweet
  • Share on Tumblr
  • Email
  • Print

Like this:

Like Loading...

Reader Interactions

Comments

  1. Bob says

    May 20, 2021 at 9:16 am

    Dab is the absolute worst road builder I have ever witnessed. They should never be given another project. SR 54 between east of Curlet to Avalon Park is just forgotten about. It’s been over a month or more since any work has been performed on the listed area. It is sickening to look at our roads in such disarray because of a company that cannot perform

    Log in to Reply

Leave a Reply Cancel reply

You must be logged in to post a comment.

Primary Sidebar

Search

Sponsored Content

6 Reasons to Consider Remodeling your Bathroom with CMK Construction

March 21, 2023 By Kelli Carmack

Have you wanted to remodel your bathroom for a while now, but need that little extra push to make your decision? Check … [Read More...] about 6 Reasons to Consider Remodeling your Bathroom with CMK Construction

Avalon Applauds African American Club of Pasco

March 7, 2023 By Kelli Carmack

One of Avalon Park Wesley Chapel’s main missions is being a champion for culture. “Celebrating culture is a vital … [Read More...] about Avalon Applauds African American Club of Pasco

More Posts from this Category

What’s Happening

03/22/2023 – Florida Landscaping

The New River Library, 34043 State Road 54 in Wesley Chapel, will host “Florida-Friendly Landscaping 101” on March 22 at 2 p.m. Participants can learn how to create a successful home landscape by following the nine Florida-Friendly program principles. Register online at PascoLibraries.org. … [Read More...] about 03/22/2023 – Florida Landscaping

03/23/2023 – Betmar Chorus

The Betmar Chorus will perform its annual Spring Concert on March 22 at 2 p.m., and on March 23 and March 24 at 7 p.m., at Betmar Acres, 37145 Lakewood Drive, Clubhouse 2, in Zephyrhills. Doors will open at 6:30 p.m. The choir will perform a variety of show tunes, hymns, spirituals and classics. Tickets will be available at the door for $5. For information, all 810-837-0520. … [Read More...] about 03/23/2023 – Betmar Chorus

03/23/2023 – Free Food Distribution

The Pasco Sheriff’s Office, Farm Share, Veteran’s Memorial Park, the Gentlemen’s Course, Samaritan Corporation of Pasco County Inc., and the Pasco County NAACP will team up for a free community food distribution on March 23 at Veterans Memorial Park, 14333 Hicks Road in Hudson. The food will be distributed on a first-come, first-served basis from 9 a.m., until the items run out. … [Read More...] about 03/23/2023 – Free Food Distribution

03/23/2023 – Paint with Puppies

B Creative Painting Studio, 6013 Wesley Grove Blvd., Suite 103, in Wesley Chapel will host “Paint with Puppies” on March 23 from 6 p.m. to 8 p.m., in support of the Mercy Full Project. Guests can get creative and cuddle with puppies. Only 50 spots available. An RSVP and $5 deposit is required online at tinyurl.com/PaintWithPuppy. Balance will be due at the event. The total cost of $50 includes a dog bowl, paint, glaze and fire of the bowl. … [Read More...] about 03/23/2023 – Paint with Puppies

03/23/2023 – Puzzle Club

The Land O’ Lakes Library, 2818 Collier Parkway, will host a Puzzle Club on March 23 at 4:45 p.m., for ages 18 and older. Bring some friends. Puzzles will be provided. For information, call 813-929-1214. … [Read More...] about 03/23/2023 – Puzzle Club

03/25/2023 – America is Awesome

Lucas, Macysyzn & Dyer, Injury Lawyers and the Lucas, Macyszyn & Dyer Community Foundation will host an “America is Awesome Celebration” on March 25 from 3 p.m. to 10 p.m., at St. George Greek Orthodox Church, 9426 Little Road in New Port Richey. The event will include live music from 5 Shades of Grey and Southbound 75; fireworks; a DJ dance party, silent auction; raffles; 50/50; car show, food and drink; and more. All proceeds will benefit K9 for Partners and local law enforcement. General admission is free. VIP tickets are available. Donations for parking will be accepted. For information, visit America is Awesome Celebration on Facebook. … [Read More...] about 03/25/2023 – America is Awesome

More of What's Happening

Archives

 

 

Where to pick up The Laker and Lutz News

Copyright © 2023 Community News Publications Inc.

   
%d bloggers like this: