• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to secondary sidebar
  • About Us
  • Videos
  • Online E-Editions
  • Social Media
    • Facebook
    • Twitter
    • Instagram
  • Advertising
  • Local Jobs
  • Puzzles & Games
  • Circulation Request

The Laker/Lutz News

Serving Lutz since 1964 and Pasco since 1981.
Proud to be independently owned.

Serving Pasco since 1981/Serving Lutz since 1964

  • Home
  • News
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills/East Pasco
    • Business Digest
    • Senior Parks
    • Nature Notes
    • Featured Stories
    • Photos of the Week
  • Sports
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills and East Pasco
    • Check This Out
  • Education
  • Pets/Wildlife
  • Health
    • Health Events
    • Health News
  • What’s Happening
  • Closer Look
  • Homes
  • Obits

Suncoast Parkway

State road projects will ease congestion

January 12, 2021 By Special to The Laker/Lutz News

Orange traffic cones and road signs signaling “a new traffic pattern” are a common sight for motorists, especially those traveling Pasco County’s state highway grid.

Amid COVID-19 lockdowns and now hopefulness that a vaccine could mean a return to normalcy, roadwork in Pasco County never stopped. Construction crews cleared rights of way, smoothed out dirt, buried pipes, paved new traffic lanes, landscaped medians, added pedestrian and bicycle lanes, and realigned existing roadways to ease traffic congestion in one of Tampa Bay’s fastest-growing counties.

Several major road projects from the Florida Department of Transportation (FDOT) will be completed within the next four years. They include work on a new diverging diamond interchange at State Road 56 and Interstate 75, as well as projects on State Road 54 and State Road 52.

The construction schedules haven’t always met expectations.

Pasco County commissioners recently expressed displeasure with the slower than anticipated pace of project completions, especially on the diverging diamond. Pasco officials pushed to get the project started early, hoping for a spring 2021 completion. Instead, the schedule promises a summer 2022 end date, according to FDOT officials.

The new interchange is an entry and exit off I-75 onto State Road 56 where commercial and residential development is bringing new retail, hotels and residents to the area. Among the destinations are Cypress Creek Town Center, Tampa Premium Outlets and AdventHealth Center Ice.

The first completed road project is expected in late 2021 when work ends on the widening of State Road 54 east of Curley Road to east of Morris Bridge Road. The last project through the pipeline will be the widening and realignment of State Road 52 in summer 2024.

Here is a list of some major state road projects currently under construction in Pasco County:

Workers from Sodmore LLC, of O’ Brien, lay sod for the diverging diamond interchange at Interstate 75 and State Road 56, just west of Willow Oak Drive. The new interchange, scheduled to be completed in summer 2022, is expected to relieve traffic snarls at the interchange. (Fred Bellet)

Interstate 75 at State Road 56 diverging diamond interchange
Construction began in January 2019, with a completion scheduled in summer 2022. The estimated cost is about $33 million.

The diverging diamond is a popular design innovation with a unique pattern that relies on multiple lanes of traffic in a crisscross pattern and a limited number of traffic signals.

This project is the first diverging diamond in District 7 of the FDOT. Others are planned in Hillsborough County at State Road 54 and Martin Luther King Jr. Boulevard, at I-75; and at Gibsonton Drive, at I-75.

FDOT’S website praises the diverging diamond for its ability to handle heavy traffic volumes, increased pedestrian safety, more efficient signal timings and fewer opportunities for vehicles to crash.

Interstate 75 at Overpass Road
Construction on a new diamond interchange, including changes to local road patterns, began in October 2020. Completion of the approximately $64 million project is scheduled for summer 2023.

The new interchange is located about 3.5 miles south of State Road 52. There will be a flyover for westbound Overpass Road access onto southbound I-75.

Overpass will be widened from two to four lanes between I-75 and Old Pasco Road, and to six lanes between I-75 and Boyette Road. Blair Drive will be realigned to connect with Old Pasco Road, and McKendree Road will be realigned to connect to Boyette.

Initially, crews will work in the southwest area of the project where a new neighborhood access road will be built at Old Pasco Road. It will replace the current Blair Drive link to Overpass.

Motorists westbound on State Road 54 make their way into Wesley Chapel as eastbound motorists head into Zephyrhills. The state road is being widened from two lanes to four lanes, with a median, to ease traffic congestion.

State Road 54 widening in the Wesley Chapel and Zephyrhills areas
About 4.5 miles of State Road 54 will be widened from two lanes to four lanes from east of Curley Road to east of Morris Bridge Road.

Construction began in November 2017 and is scheduled for completion in late 2021. The estimated cost is $42.5 million.

In early November, eastbound traffic shifted onto newly paved lanes from west of Wesley Chapel Loop to New River Road. Simultaneously, Pasco is remodeling the New River Branch Public Library on State Road 54.

A sidewalk will be built on the north side of the roadway with a 10-foot-wide multi-use path on the south side.

State Road 52 widening and realignment near Dade City and San Antonio
The project will widen and realign State Road 52 between Uradco Place and Fort King Road.

Construction began in November 2019, with completion scheduled in summer 2024. The estimated cost is $81.4 million.

A short portion of McCabe Road between Curley Road and Wirt Road is closed until spring 2021. Williams Cemetery Road is closed east of Wichers Road and McCabe, also until spring 2021.

In addition, some daily lane closures, with flagmen signaling to motorists, can be expected on Curley, McCabe, Prospect Road and Clinton Avenue. A detour route is available using Curley, Prospect and Wirt.

State Road 52 widening in Land O’ Lakes
About 3.8 miles of State Road 52 will be widened into a six-lane divided road from Suncoast Parkway to east of U.S. 41.

Construction began in September 2019, with completion scheduled in late 2023. The estimated cost is $49.8 million.

A 12-foot-wide multi-use path will be built on the north side of State Road 52. In addition, about one mile of U.S. 41 will be widened as it approaches the intersection with the state road.

By Kathy Steele

Published January 13, 2021

Filed Under: Top Story Tagged With: AdventHealth Center Ice, Blair Drive, Clinton Avenue, Curley Road, Cypress Creek Town Center, Diverging Diamond, FDOT, Florida Department of Transportation, Fort King Road, Gibsonton Drive, Interstate 75, Martin Luther King Jr. Bouleard, McKendree Road, Morris Bridge Road, New River Branch Public Library, New River Road, Old Pasco Road, Overpass Road, Prospect Road, State Road 52, State Road 54, State Road 56, Suncoast Parkway, Tampa Premium Outlets, U.S. 41, Uradco Place, Wesley Chapel Loop, Wichers Road, Williams Cemetery Road, Wirt Road

ICI Homes’ Exclusive Builder In Asturia’s Final Phase

December 29, 2020 By Special to The Laker/Lutz News

If you dream of building a new home in Pasco County’s in-demand State Road 54 corridor, look no further than the final phase of Asturia in Odessa.

ICI Homes — one of Florida’s best-known and prestigious builders — has been chosen as the exclusive builder in Asturia’s final phase, with 23 over-sized homesites in this exclusive community located just minutes from the Suncoast Parkway.

“We are so excited to have these final homesites in Asturia, where we have been building beautiful homes for area families since 2017,” said Greg Jones, Tampa division manager for ICI Homes. “These new homesites are some of the prettiest in all of Asturia, with many backing up to conservation, and all offering privacy and quick access to State Road 54.”

Phase 4 road construction and infrastructure are underway, and ICI Homes is now offering pre-construction sales to its VIP families.

“Because of Asturia’s stellar reputation as a great place to live, we are anticipating a huge demand for these new homesites” said Jones. “These are the final lots in this highly desirable community, and we expect them to sell fast. We encourage people to call today for a VIP appointment to secure their desirable homesite before they are gone.”

Asturia is situated on 500 pristine acres in central Pasco on the north side of State Road 54. Setting it apart from other master-planned communities is Asturia’s manageable size of just 550 homes. It is a friendly, walkable development that promotes a healthy, active lifestyle with its many trails, walkways, parks and recreational amenities.

Outstanding schools are another top reason why families chose Asturia. Children attend some of the best schools in the county, including Odessa Elementary, Seven Springs Middle School and J.W. Mitchell High School. All three schools have received a minimum A or B school grade for the last three years.

ICI Homes is building several floor plans in Asturia. After its final 23 homes are completed, it will close out all new construction in the community, which began development in 2016.

Many of ICI Homes will back up to incredible wilderness views of wetlands, cypress trees and rolling ranchland. Wildlife is everywhere, and residents will enjoy connecting community trails perfect for bird-watching, and to see deer, gopher tortoises, racoons and other native animals.

ICI Homes has chosen its most popular one- and two- story floor plans for Asturia, all with family friendly layouts, where cooking, dining, relaxing and entertaining happen cohesively. Homes feature an abundance of windows that bring the outside in.

Floor plans include the Costa Mesa, which also is its model home, that is open now for folks who want to stop by to get more information about Phase 4 from Rich Driver, ICI Home’s dedicated and longtime sales representative for Asturia.

The Costa Mesa is a one-story home that showcases 2,565 square feet of living area, with four bedrooms, three baths and a three-car garage. It is designed for all kinds of families — young professionals just starting out, those with young and school-aged children, and empty-nesters.

“The Costa Mesa’s open floor plan is perfect for entertaining,” said Driver. “Its gathering room, gourmet kitchen and dining room are one expansive space highlighted by lots of windows that capture tons of natural light.”

The model is located at 2112 Secret Cove in Odessa, and is open 10 a.m. to 6 p.m., Monday through Saturday, and noon to 6 p.m., on Sunday. All COVID-19 safety restrictions are in place, including masks and social distancing. To schedule your VIP appointment, stop by the model to see Rich, call (813) 252-1108, or go to ICIHomes.com.

Lake Jovita and Persimmon Park
ICI Homes also is accepting VIP reservations for new homesites in Lake Jovita Golf and Country Club in Dade City, and continues to build homes in Persimmon Park in Wesley Chapel in the Wiregrass Ranch community. Both communities are tremendously successful and are attracting families of all kinds because of their unique ICI design features and community amenities.

A new Lake Jovita Sales Center has recently opened at 12330 Lake Jovita Blvd., Dade City, FL 33526. The model center at Persimmon Park is located at 3793 Lajuana Blvd., Wesley Chapel, FL 33543.

Since ICI Homes was established in 1980, the company has built over 4,000 single-family homes in Florida, including the Tampa Bay area, and has earned several prestigious awards for design and innovation.

Published December 30, 2020

Filed Under: Home Section, Sponsored Content Tagged With: Asturia, Greg Jones, ICI Homes, J.W. Mitchell High School, Lajuana Boulevard, Lake Jovita Boulevard, Lake Jovita Golf and Country Club, Odessa, Odessa Elementary, Persimmon Park, Rich Driver, Secret Cove, Seven Springs Middle School, State Road 54, Suncoast Parkway, Wiregrass Ranch

Construction, legal action on Ridge Road

December 29, 2020 By Special to The Laker/Lutz News

Work on the Ridge Road extension is pushing ahead even as legal action from the Sierra Club to halt construction remains active.

Attorneys for the Sierra Club recently filed a motion to add U.S. Fish and Wildlife Service as a defendant in a lawsuit that was filed in February against the U.S. Army Corps of Engineers.

The approximately 9-mile corridor would link Moon Lake Road in New Port Richey with the Suncoast Parkway, and eventually will reach U.S. 41 in Land O’ Lakes.

An aerial view shows a portion of the Ridge Road extension route beginning with Moon Lake Road in New Port Richey and linking to U.S. 41 in Land O’ Lakes. (Courtesy of Pasco County)

The extension cuts through the Serenova Tract of the Starkey Wildlife Preserve, which has been a point of contention.

Environmentalists say the road will destroy sensitive conservation wetlands and wildlife habitats. They believe the motive for the road extension is to support more growth and development.

The lawsuit alleges that Fish and Wildlife in its “biological opinion” violated the Endangered Species Act and failed to properly assess harmful impacts, specifically to the Eastern indigo snake. The lawsuit also claims the Army Corps failed to complete a legally required comprehensive analysis on impacts to the Florida scrub blue jay and the red-cockaded woodpecker.

“They are causing damage to the best preserve in Pasco County,” said Tim Martin, chair of the Sierra Club Florida’s conservation committee.

County officials say the road extension will add a vital east/west evacuation route during hurricanes and other emergencies. The route and construction seek to do minimal damage to the preserve, they say.

The Serenova Tract is part of a 1990s settlement agreement reached during litigation over construction of the Suncoast Parkway. About 200 acres were set aside to mitigate wetlands damage. Ownership transferred from the Florida Department of Transportation to the Southwest Water Management District, but preserved the right to extend Ridge Road.

Battle lines over the proposed route put county officials and environmental activists on opposing sides for more than 20 years. But, in late 2019, the Army Corps granted a construction permit.

In March, a federal judge denied a Sierra Club motion for an emergency injunction to temporarily block road construction until the lawsuit’s conclusion. The decision cited “monetary harm” to the county if work were halted.

Roadwork moved ahead.

And, in November, Pasco County commissioners approved approximately $2.7 million to purchase wetland mitigation credits due to “unavoidable wetlands impact.”

Last summer work crews completed a road segment linking Ridge Road and Town Center Boulevard, an access point for River Ridge Middle and High Schools.

Next up is building a two-lane segment between Town Center and the Suncoast Parkway, with an expected completion in summer 2021. The two-lane roadway later will be widened to four lanes by summer of 2022.

Construction is expected to begin in 2021 on the Ridge Road extension between Suncoast Parkway to the future Suncoast Boulevard. The final step would be extending Ridge Road from the boulevard to U.S. 41 at the intersection with Connerton Boulevard, the main entrance into the master-planned community of Connerton.

Construction on this segment would begin in 2022.

County officials hope to open the entire Ridge Road extension by the end of 2025.

In addition to the roadway, as many as 16 bridges will provide overpasses along the length of Ridge Road. There also will be pathways, upland wildlife crossings and fences to provide habitat connectivity, and prevent roadkill of the numerous species living in the preserve.

Work crews cleared a swath of land to prepare for construction of the Ridge Road extension.

The initial phase of the project is estimated at $93.2 million, including incentives to finish early. About $11.3 million will pay for ramps and toll equipment at the Suncoast Parkway interchange. The final phase of construction is about $36.1 million. However, county officials said the design and cost estimate of that phase will be updated by the end of 2020.

Martin said the county is moving aggressively to complete construction. If the Sierra Club prevails in its efforts to permanently stop the road extension, Martin said, “We want them to restore it to its natural state.”

Sierra Club attorney Sarah Hayter said the goal is to have the permit revoked. Though the county is spending millions, Hayter said the courts could require Pasco to restore what it has done.

A federal judge must determine if Fish and Wildlife can be added to the lawsuit, said Hayter. Representatives for Fish and Wildlife, and the Army Corps, agreed to the amended lawsuit, she said.

However, Hayter said she understood that Pasco officials planned to file an objection.

Pasco isn’t a defendant in the lawsuit, but the courts granted a request for the county to intervene on behalf of the Army Corps.

County officials declined to comment on pending litigation.

By Kathy Steele

Published December 30, 2020

Filed Under: Top Story Tagged With: Connerton, Connerton Boulevard, Endangered Species Act, Florida Department of Transportation, Moon Lake Road, Ridge Road, River Ridge High School, River Ridge Middle School, Sarah Hayter, Serenova Tract, Sierra Club, Southwest Water Management District, Starkey Wilderness Preserve, Suncoast Boulevard, Suncoast Parkway, Tim Martin, Town Center Boulevard, U.S. 41, U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service

Design work begins on new Land O’ Lakes school

August 18, 2020 By B.C. Manion

Pasco County Schools has signed a contract with Harvard Jolly Architecture for the design of a new 6-12 School to be built within the Angeline community of Land O’ Lakes.

The architect will be paid nearly $3 million, under terms of the contract approved by the Pasco County School Board on July 28.

The school will be built on an 18-acre site, with a capacity for 1,694 students.

The estimated construction budget is $45 million.

Construction is expected to begin in December of 2021, with completion expected by June 2023.

The construction manager will provide construction management services, with a guaranteed maximum price. The project also will be designed in compliance with a sustainable building rating system.

The school is part of a new community that is expected to become a major job generator, and to be a place where people will live, work, play and learn.

The proposed development — referred in economic development documents initially as Project Arthur, is now known more commonly as the Angeline community.

It is being planned on 7,000 acres, in an area south of State Road 52, east of the Suncoast Parkway and west of the CSX rail line.

Plans call for a 24-million-square-foot corporate business park, which is expected to create large-scale employment opportunities. Supportive services also are envisioned, including residential communities, parks, schools and other uses to be connected through walking and bike trails, the report adds.

The property — which has uplands and wetlands areas — has been used for cattle ranching and a pine plantation for decades, according to a county report.

The landscape includes oaks and pine trees, and forested and non-forested wetlands. It also has open water lakes, which are mostly remnants from prior borrow pit operations, according to the county report.

The report also notes that the project site’s proximity to the CSX railroad line provides an opportunity for commuter rail, in the event that the rail line is converted to a commuter rail line in the future.

Two of the county’s vision roads also go through the project: Ridge Road and Sunlake Boulevard.

The extension of Ridge Road, and the construction of a new interchange at Ridge Road and the Suncoast Parkway also will have a significant impact on the area’s development.

Lee Moffitt Cancer and Research Institute has purchased about 775 acres for a future research hub near the interchange.

Published August 19, 2020

Filed Under: Education, Land O' Lakes News, Local News Tagged With: Angeline, Harvard Jolly Architecture, Land O' Lakes, Lee Moffitt Cancer and Research Institute, Pasco County School Board, Pasco County Schools, Project Arthur, Ridge Road, State Road 52, Suncoast Parkway, Sunlake Boulevard

Amazon plans $40 million investment in Pasco

August 11, 2020 By B.C. Manion

The Pasco Economic Development Council has announced that Amazon plans to invest $40 million in Pasco County.

The company is planning a new 110,000-square-foot facility in Lutz, according to a Pasco EDC news release.

The facility will be located on a portion of the Hayman-Fuentes property near the northeast corner of State Road 54 and the Suncoast Parkway, according to Lauren Miceli, marketing and communications manager for Pasco EDC.

“This new facility will add hundreds of direct and indirect jobs to Pasco County,” Bill Cronin, president/CEO of Pasco EDC, said in the economic development agency’s release.

The new delivery station in Lutz “will power Amazon’s last-mile delivery capabilities to speed up deliveries for customers in Pasco County,” according to an Amazon news release.

“Delivery stations enable Amazon Logistics to supplement capacity and flexibility to Amazon’s delivery capabilities,” the company release says.

The Lutz delivery station is expected to open in 2021, according to Amazon.

Local officials are delighted by Amazon’s decision to invest in Pasco.

“Amazon’s jobs are unique in the sense that some will work directly for the company and others can essentially open their own business and work as a third party with them. It’s a great opportunity for our residents to start their own small business,” Cronin added.

“The county and Pasco EDC have worked hard to create mixed-use neighborhoods and attract a variety of industries to Pasco,” Pasco County Commissioner Mike Wells said in the Pasco EDC release. “Amazon putting their trust that Pasco is the right place for them shows that our team’s hard work is paying off and we welcome them to our community.”

Amazon’s delivery stations offer entrepreneurs the opportunity to build their own business delivering Amazon packages, as well as independent contractors the flexibility to be their own boss and create their own schedule delivering for Amazon Flex.

Amazon has more than 150 delivery stations in the United States.

Pasco County Commission Chairman Mike Moore reacted to the news, in an Amazon release that announced the company’s upcoming Tampa Bay plans.

“I am thrilled to welcome Amazon and the additional jobs this facility will bring to our community,” Moore said, in the release. “This is another example of Pasco County government and the Pasco Economic Development Council working together to make Pasco County the premier place for business.”

In addition to its planned Lutz facility, the company also has announced a new fulfillment center in Temple Terrace, which is expected to create 720 jobs. That, too, is expected to launch in 2021.

Amazon currently operates seven fulfillment and sortation centers in the state, in Jacksonville, Davenport, Orlando, Miami, Ruskin and Lakeland, according to a company news release.

Amazon’s new operations facility in Temple Terrace will span more than 600,000 square feet on the ground floor. Employees at the site will work alongside innovative technologies to pick, pack and ship smaller customer items, such as books, electronics, small household goods and toys, the Amazon release says.

Amazon will hire for roles in human resources, operations management, safety, security, finance and information technology.

Amazon offers a minimum starting wage of $15 per hour. Its full-time employees also receive full medical, vision and dental insurance, as well as a 401(k), with a 50% company match, beginning on Day 1.

To learn more about Amazon, visit Amazon.com.

Published August 12, 2020

 

Filed Under: Top Story Tagged With: Amazon, Amazon Logistics, Bill Cronin, Lauren Miceli, Lutz, Mike Moore, Mike Wells, Pasco Economic Development Council, Pasco EDC, State Road 54, Suncoast Parkway

Pasco eyeing rule changes to spur more jobs

July 21, 2020 By B.C. Manion

The Pasco County Commission is looking at changing the county’s employment center land use requirements in an effort to encourage more jobs.

County Commissioner Jack Mariano raised the issue during the board’s July 14 meeting, noting that he’s aware of a potential development near the intersection of State Road 54/Suncoast Parkway that could yield more jobs, if the site wasn’t required to have a multifamily component.

“I don’t want to restrict anybody, with EC (an employment center designation), not to be able to create more jobs,” Mariano said. “I want to get every single job that I can.”

Commission Chairman Mike Moore chimed in: “I agree. Do we want apartments or 500 more jobs? We want the jobs. It’s not hard to figure out, right?”

Moore said that’s especially true along the State Road 54/56 corridor, which already has a substantial amount of housing available.

Commissioner Mike Wells said he also supports Mariano’s position.

Nectarios Pittos, the county’s planning and development director, reminded commissioners that it has been the county’s longstanding policy to locate housing close to employment.

He also noted that the county’s plan promotes creating density to support transit plans.

Sites designated as employment centers that are 20 acres or less are not required to include multi-family development, Pittos added.

He also cautioned commissioners that such a change could contribute to traffic congestion.

Commissioner Kathryn Starkey said the board needs to hear the pros and cons of making such a change.

“We’re making some knee-jerk reactions,” Starkey said. “We only have two east-west roads. We need to be careful.”

Commissioners directed county staff to prepare a board workshop for further discussion on the issue.

In other action, the board:

  • Approved a resolution to notify the public of the county’s proposed solid waste rate increase of $7 per equivalent residential unit (single-family) for fiscal year 2021. The resolution also includes a proposed increase in per-ton tipping fees of $6.39 per ton for fiscal year 2021. A public hearing on the proposed increases has been set for Sept. 8 at 9 a.m., in the board chambers of the Historic Pasco County Courthouse, at 37917 Meridian Ave., in Dade City.
  • Approved an amendment to an agreement with Good Samaritan Health Clinic of Pasco Inc., to extend the time to complete the installation of a generator for the pharmacy and medical flooring for the clinic. The original completion date was scheduled for Sept. 30, 2020. However, due to COVID-19, an extension was necessary. The new completion deadline is Sept. 30, 2021.
  • Promoted Brian Hoben to the position of community services director. Hoben had been serving as the public services administrator and as interim community services director.

Published July 22, 2020

Filed Under: Local News Tagged With: Brian Hoben, Dade City, Good Samaritan Health Clinic of Pasco, Jack Mariano, Kathryn Starkey, Meridian Avenue, Mike Moore, Mike Wells, Nectarios Pittos, Pasco County Commission, Pasco County Courthouse, State Road 54, State Road 54/56, Suncoast Parkway

Ridge Road construction moves forward

June 30, 2020 By Kathy Steele

By summer, motorists could take their first spins along the initial segment of the Ridge Road extension from Moon Lake Road/DeCubellis Road to Town Center Boulevard.

“We’re hoping we open that leg by the start of August, for the start of the school year,” said Sam Beneck, Pasco County’s property manager. “They are pulling out all the stops to get it done. It’s going to be a real challenge.”

The roadwork is expected to ease traffic for River Ridge high school and middle school along Town Center.

This aerial view shows the area where Ridge Road construction will begin at Moon Lake in west Pasco County. (Courtesy of Pasco County)

This short jog forward is the beginning of a two-phased road project, with a final completion date in 2025. By then, the approximately 8.6-mile extension of Ridge Road, from west to east, is expected to cross over Suncoast Parkway and come out at U.S. 41, opposite an entrance into the master-planned community of Connerton in Land O’ Lakes.

Pasco County officials celebrated the kick-off to Ridge Road’s extension in January. It was the culmination of more than two decades of pushing the U.S. Army Corps of Engineers to issue a permit that would allow the new road to cut through sensitive environmental land in the Serenova Tract of the Starkey Wilderness Preserve.

For years, county officials identified the east/west route as an essential evacuation route during hurricanes and other emergencies. They expect it to take pressure off existing east/west routes of State Road 52 and State Road 54, and cut evacuation times down by hours. In addition, traffic capacity is expected to increase by 10%.

“It’s really to improve traffic capacity and east/west access to improve hurricane evacuations,” said Beneck. “We really, really see it as a significant evacuation improvement with multi-hour benefits in reaching our evacuation goal and traffic capacity. There was never another alternative that provided these benefits.”

Environmentalists suggest that the north/south route of U.S. 19 makes more sense for evacuations, and would avoid harm to the Serenova.

“We need to maintain our natural systems and forests to mitigate against climate change,” said Tim Martin, conversation chairman for the Sierra Club Florida. “We just need to leave our natural systems and keep our preserves preserved.”

Sierra Club Florida Conservation filed a lawsuit against the Army Corps in February in the U.S. Middle District of Florida. However, a judge denied an emergency injunction to stop the roadway. Pasco County, which is not a defendant in the lawsuit, was granted permission to intervene in the case.

The Sierra Club alleges that the Army Corps violated the National Environmental Policy Act and failed to adequately evaluate the harm to threatened and endangered species within the Serenova, and to their habitats and wetlands.

Martin said county taxpayers need to understand they could be the losers if the lawsuit is successful and Pasco is ordered to restore wetlands that the roadway is destroying.

Beneck said the county is sensitive to the impacts to the Serenova. County staff and the Fish and Wildlife Commission have provided guidance on mitigation efforts, including relocating gopher tortoises found on site.

The court date is pending.

When completed, the roadway through the Serenova will have 16 bridges that cross over wetlands, and wildlife crossings at 15 of those bridges.

Landscaping and multi-use paths will be installed with nature overlooks that allow for relaxation and observation.

The total estimated cost of the project is more than $149 million, with the largest share – about $93.2 million – paying for phase one from Moon Lake to the Suncoast. Suncoast to Sunlake is estimated to cost about $12.7 million. Funding sources for the $44 million final segment from Sunlake to U.S. 41 are identified and will be budgeted in the fiscal year 2023, based on revenue estimates and projections, according to county officials.

The Florida Turnpike Authority will fund the new interchange at Ridge Road and the parkway.

The interchange and surrounding land are attracting new development.

Lee Moffitt Cancer and Research Institute recently purchased about 775 acres for a future research hub near the interchange.

Lennar, which sold land to Moffitt, is proposing a master-planned community of Angeline, formerly Project Arthur, that would transform a former cattle ranch and pine plantation into a residential and commercial community. The property is located south of State Road 52 and east of Suncoast. Both Ridge Road and Sunlake Boulevard cut through the property.

Environmentalists say these types of projects are the true reason for extending Ridge Road.

“Now, it’s pretty obvious all along they had bigger plans for opening central Pasco,” said Martin. “A lot of this is bad growth and sprawl.”

One design change in Ridge Road could add as many as seven signalized intersections to the phase two, at-grade construction of roadway from Suncoast to Land O’ Lakes boulevard.

While this segment initially had limited access, county officials later designated it an arterial roadway in acknowledgement that private property owners might develop land adjacent to Ridge Road.

However, Beneck said Pasco planned for Ridge Road based on the county’s long-range comprehensive plan, not any specific development projects. “We really hadn’t heard of any development plans.”

It would be up to private developers to seek any necessary permits, he said.

“Private developers would be responsible for doing all of their own mitigation,” Beneck said.

Published July 1, 2020

Filed Under: Local News Tagged With: Connerton, DeCubellis Road, Fish and Wildlife Commission, Florida Turnpike Authority, Land O' Lakes, Lee Moffit Cancer and Research Institute, Lennar, Moon Lake Road, National Environmental Policy Act, Ridge Road, River Ridge High School, River Ridge Middle School, Sam Beneck, Serenova Tract, Sierra Club Florida, Sierra Club Florida Conservation, Starkey Wilderness Preserve, State Road 52, State Road 54, Suncoast Parkway, Sunlake, Tim Martin, Town Center Boulevard, U.S. 19, U.S. 41, U.S. Army Corps of Engineers

Top Parade of Homes Awards For ICI Homes

June 23, 2020 By Special to The Laker/Lutz News

It’s always exciting for a builder to be recognized in a community’s Parade of Homes competition, but this year ICI Homes outdid itself by winning two of the most prestigious awards in Tampa Bay.

In early March, a total of 79 homes were entered in the Parade of Homes from a variety of builders and developers, in the competition organized by the Tampa Bay Builders Association. And, once again, ICI Homes — a relatively new builder in the Tampa market — was chosen to receive two of its top honors.

The top award went to its Costa Mesa model in Asturia, a master-planned community in Odessa where ICI Homes has been building for the past three years. The Costa Mesa was honored with the Grand Award in the $600k-$649k price range — one of the most competitive categories in the Parade of Homes.

This 2,565-square-foot model home is absolutely stunning. A huge kitchen and extra-large island sets apart this spacious, one-story home that features four bedrooms, three baths and a three-car garage. One of its most unique features is a closet-size, walk-in pantry that is hidden behind beautiful kitchen cabinetry.

The builder’s second big win is for its Lantana model, which won a Silver Award in the $350k-$399k price range. This 1,800-square-foot home is one of six new floor plans that ICI Homes is introducing in Persimmon Park, a brand new community in Wesley Chapel within the master-planned development of Wiregrass Ranch.

The Lantana model at Persimmon Park in Wesley Chapel won a Silver Award at the recent Tampa Bay Parade of Homes.

Located off Bruce B. Downs Boulevard and directly behind The Shops at Wiregrass and AdventHealth Wesley Chapel, Wiregrass Ranch is a 5,000-acre, walkable community with trails that lead to parks, schools, entertainment, recreation and top-notch medical facilities.

“Persimmon Park gives our residents immediate access to all that Wiregrass Ranch and Wesley Chapel have to offer,” said Rosemary Messina, vice president of marketing and sales. “And, adding to the community’s appeal are amenities that families want, but without going overboard — a unique T-shaped pool and cabana, outdoor grilling, interconnecting trails, and dog parks for small and large breeds.”

The winning Lantana floor plan has a spacious kitchen/great room, with a large dining room and open flex room connecting to the kitchen. The master bedroom is at the rear of the home to give easy access to the garage, covered lanai and main living area. The one-story model is the craftsman elevation and, at 1,793 square feet, also offers two bedrooms and a bath at the front of the home.

All of ICI Homes in Persimmon Park have open floor plans with front porches, and garages and alleys at the back of the home. The first phase has 40 homes, with prices beginning in the high $200s.

Light and bright with lots of windows is how Messina describes the cottage-style floor plans at Persimmon Park. “Our plans feel open and airy, and exemplify Florida’s casual lifestyle,” she says. “These homes are designed for people wanting to simplify their life, who want less square footage to clean and maintain, yet want all the upscale finishes and details offered by ICI Homes.”

Inventory Homes In Asturia
In Asturia, ICI Homes has four inventory homes that are ready now or will be available soon. Two homes are of the award-winning Costa Mesa floor plan and one is a two-story Palisade. A one-story Arden will soon be completed.

“All of our floor plans are perfect for entertaining,” said Messina. “Our gathering rooms, gourmet kitchens and dining rooms blend together as one expansive space, highlighted by lots of windows that capture tons of natural light.”

ICI Homes has over 25 homesites remaining in Asturia, with many backing up to conservation and water. Prices begin in the high $300s. This 550-home community includes a unique trail system that winds through wetlands, parks and neighborhoods, and an award-winning Amenity Center that is known for its zero-entry pool, contemporary community center and state-of-the-art fitness center.

Bexley Showpiece
This is the last chance to buy an ICI Home in the first phase of Bexley, a master-planned community in Land O’ Lakes with thousands of acres of preserved wetlands, miles of recreational trails and a great location off State Road 54 and the Suncoast Parkway.

The builder’s Egret VII inventory home is one of the most beautiful and functional move-in ready homes available in Bexley. This one-story, four-bedroom, three-bath home has 2,813 square feet of living space, and features luxury finishes, an extended lanai, deluxe kitchen, huge gathering room and, at the home’s grand entrance, a large dining room and flex room. Separate from its side-entry two-car garage is a tandem garage ideal for a compact car, golf cart or storage.

This beautiful home sits on a 70-foot corner homesite in one of Bexley’s most prestigious neighborhoods, located close to the clubhouse and pools.

Published June 24, 2020

Filed Under: Home Section Tagged With: AdventHealth Wesley Chapel, Asturia, Bexley, Bruce B. Downs Boulevard, ICI Homes, Land O' Lakes, Parade of Homes, Persimmon Park, Rosemary Messina, State Road 54, Suncoast Parkway, Tampa Bay Builders Association, The Shops at Wiregrass, Wesley Chapel, Wiregrass Ranch

New interchange will ease congestion

June 16, 2020 By Kathy Steele

Construction crews could be turning dirt within months on a new interchange at Interstate 75 and Overpass Road.

A contractor is expected to be selected by August, and completion is expected about 2 ½ years after construction begins.

The junction frequently is identified as a “gateway” into Pasco County, and a potential catalyst for new development in a largely rural area already experiencing a burst of growth.

The new I-75/Overpass Road interchange is expected to significantly reduce the volume of vehicles per day here and at two other interchanges. (Courtesy of Pasco County)

“It has a regional impact for Pasco,” said Bill Cronin, president and chief executive officer of the Pasco Economic Development Council. “Another exit opens into the county where we have potential for residential and commercial growth. That is another big gateway for Pasco County from the north but from the east, too.”

On a more local scale, the new interchange is expected to ease traffic congestion, bring more connectivity to northeast Pasco cities, and give the county another evacuation route for hurricanes and other emergencies.

“The benefit to the county is just tremendous,” said Margaret Smith, Pasco’s director of engineering services. “We’re giving residential and commercial users a whole other entrance. It takes the volume of traffic off the two busiest interchanges.”

Margaret Smith

Situated about halfway between I-75 interchanges with County Road 54 and State Road 52, traffic engineers estimate a reduction of about 13,000 vehicles per day at each interchange.

It also opens up an east/west route that aids current development in the area, including the futuristic Connected City and its Crystal Lagoon, as well as the Villages of Pasadena Hills.

Once the contractor is selected, final design details will be completed. Conceptually, though, the interchange is expected to be a modified diamond exchange with a flyover.

Pasco County is paying for the project, except for $15 million provided by the Florida Legislature. The final price tag has not yet been determined.

In this rendering, cars are eastbound as they approach the I-75/Overpass Road interchange.

The Florida Department of Transportation is partnering as managers of the project — which includes vetting the construction bids.

It’s significant that Pasco will get a new interchange along one of the major state highways in the country, Cronin said.

Interstate 75 begins in the south at Miami Lakes, Florida and passes through five states before it ends at Sault St. Marie, Michigan, on the Canadian border.

While roadwork and new development, along State Road 54, State Road 52 and the Suncoast Parkway, are highly visible, the I-75 interchange’s potential can be overlooked, Cronin said.

But, its role in attracting developers for commercial, residential and industrial projects will be significant, he added.

The new I-75/Overpass Road interchange will feature a flyover.

“You’ve got pretty good sites for industrial growth,” he said.

And, projects, such as distribution centers, built on speculation, will attract new economic development, he said.

“As soon as you announce that, 10 are in there,” Cronin said. “Space is needed so badly.”

Even Connected City, with its residential and unique Crystal Lagoon, includes industrial in its overall master plan, Cronin said.

Development in the area off the Overpass interchange is well-suited for distribution and office centers “where staff will be driving to work,” Cronin said.

That is in contrast to Suncoast Parkway development, which has “more value for people flying in and out of airports,” he added.

One beneficiary of the new interchange is a former county-owned spray field just south of Overpass Road at the interchange.

Bill Cronin, CEO and president of Pasco Economic Development Council Inc. (File)

Pasco County commissioners approved a land sale in December 2019, and an incentive package, to aid Atlanta-based Rooker Company in developing the 99-acre site as an industrial park.

In phase one, Rooker plans to build a 400,000-square-foot distribution center that is expected to bring hundreds of jobs to Pasco.

“We hope they’ll duplicate this over and over, and over again,” Cronin said.

Amid the new development, the Pasco Rural Protection Overlay District stands as a protection for rural lands and landscapes. Its borders generally are Bellamy Brothers Boulevard, the Green Swamp, State Road 52 and the Hernando County line.

Job creation and growth matters, said Cronin, but development decisions must be made with care.

“Once you use it, you can’t get it back,” he said. “There are a lot of things up there we don’t want to touch.”

In coming years, future and ongoing projects will create more east/west connections that will weave a network of new roadways. They include the Overpass interchange, but also extending State Road 56, widening and realigning State Road 52, and a realignment of U.S. 301 and U.S. 98, with connections to I-75 to the west, and Interstate 4 to the east.

“It’s coming together really well,” Cronin said. “The county has really championed this effort.”

The following highlights features of the new I-75/Overpass Road interchange:

  • Overpass Road from Old Pasco Road to I-75 will be four lanes with bike lanes, a sidewalk on the south side of Overpass, and multi-use trail on the north side of Overpass.
  • Overpass Road bridge will be four lanes with an eastbound to northbound turn-lane. The bridge will include bike lanes, a sidewalk and multi-use paths.
  • Overpass Road from I-75 to Boyette Road will be six lanes with two auxiliary lanes, bike lanes, a sidewalk, multi-use path, turn lane improvements at Overpass and Boyette, and a traffic signal.
  • A traffic signal will be installed at Old Pasco Road and Overpass.
  • Blair Drive access to Overpass will be closed, but a new two-lane road constructed from Blair to Old Pasco, south of Overpass.
  • Current McKendree Road access at Overpass will be relocated to alternate location on Boyette, north of Overpass.
  • Current secondary entry into Wesley Chapel District Park will be closed, with park entrance reconfigured for multi-modes of transportation, including for pedestrians and bicyclists.
  • Overpass between Old Pasco and Boyette will be closed for up to one year during interchange construction.

Published June 17, 2020

Filed Under: Top Story Tagged With: Bellamy Brothers Boulevard, Bill Cronin, Connected City, County Road 54, Florida Department of Transportation, Green Swamp, Hernando County, Interstate 4Interstate 75, Margaret Smith, Overpass Road, Pasco Economic Development Council, Pasco Rural Protection Overlay District, Rooker Company, State Road 52, State Road 54, Suncoast Parkway, U.S. 301, U.S. 98, Villages of Pasadena Hills

This animal control officer helps pets, and people

May 19, 2020 By B.C. Manion

Michael Northrup, who works for Pasco County Animal Services, has been named Animal Control Officer of the Year by the Florida Animal Control Association.

A nomination submitted on Northrup’s behalf said, in part, that during 2019 Northrup displayed “compassion, dedication, expertise, awareness and incredible decision-making.”

The nomination noted that Northrup responded to more than 1,000 animal control calls that year.

Michael Northrup responded to more than 1,000 animal control calls in 2019, and he helped some people along the way. His professionalism earned him the Animal Control Officer of the Year award, from a statewide organization. (Courtesy of Pasco County Animal Services)

And, while he’s an animal control officer, he’s also provided help that goes beyond the call of duty, to Pasco residents.

For example, the nomination notes, that on Aug. 9, as Northrup was driving home from work on the Suncoast Parkway he noticed cars veering around another vehicle.

As he got closer, he realized the vehicle was on fire — and, as it pulled out onto the grass, the grass caught fire, too.

Northrup pulled over, radioed Pasco Fire Rescue and the Sheriff’s Office for assistance, then he used a fire extinguisher to put out the fire.

Less than a week later, Northrup and Animal Control Officer Stephanie Martin responded to a call about loose dogs.

While there, an elderly woman told Northrup that her caregiver had been physically harming her, had moved relatives into her home and had been letting her animals run loose.

While Officer Martin talked to the caregiver, Northrup called the Florida Abuse Hotline, Pasco Fire Rescue and the Pasco Sheriff’s Office.

As a result, the elderly woman’s family moved her into assisted living, where she can get the care she needs, the nomination says.

In another case, Northrup noticed a woman was running in a dangerous intersection, yelling for someone to hit her with their car.

Northrup called to get the woman help, then waited for it to arrive.

He also helped Animal Services’ return to owner rate by 25% in one year, by reuniting more than a dozen animals to their owners in the field, without the animals having to be impounded.

Winning the award was an honor, Northrup said, but he wasn’t especially enthused about being in the spotlight.

He likes keeping a low profile and doing his job.

To be honest, he said: “I don’t like awards. I don’t like interviews. I don’t like recognition.”

When he went to work as an animal control officer, he thought the vast majority of his work would involve interacting with animals.

As it turns out, though, much of the work involves helping to mediate disputes between people regarding animals.

Calls can range from a claim that a neighbor’s dog barks too much to a report of a pack of dogs mauling someone.

“People call in crazy stuff,” he said, noting he doesn’t take complaints at face value.

“A lot of the times I find it to be more of a people problem, than an animal problem.

“A lot of times, it’s an ongoing dispute, with either one of their neighbors and they want someone to intervene — to use some type of enforcement action to alter their behavior in some way, shape or form,” he said.

“I look at every call, if I were in their shoes, how would I want that to be handled?” he said.

Frequently  he finds himself telling people something they don’t want to hear.

“You may not like what the person is doing, but that doesn’t necessarily mean they’re doing something wrong,” he said.

In other words, what seems objectionable to someone might not be a violation of a Florida Statute or a county ordinance.

“You have the right to call. We have the right to decide what we’re going to do,” he said.

“I’ve always treated everyone with firmness, fairness and dignity. Everyone deserves that,” he added.

He believes in using a straight-forward approach.

“Direct is my way of life. I usually don’t beat around the bush,” he said.

Published May 20, 2020

Filed Under: Local News, People Profiles Tagged With: Florida Abuse Hotline, Florida Animal Control Association, Michael Northrup, Pasco County Animal Services, Pasco Fire Rescue, Pasco Sheriff's Office, Stephanie Martin, Suncoast Parkway

  • Go to page 1
  • Go to page 2
  • Go to page 3
  • Interim pages omitted …
  • Go to page 17
  • Go to Next Page »

Primary Sidebar

Zephyrhills Brewing Company

Foodie Friday Gallery

Search

Sponsored Content

A New Look For 2021 From Tampa Surgical Arts

January 12, 2021 By Kelli Carmack

Tampa Surgical Arts offers cosmetic treatments that give patients confidence and makes them look years younger. Two of … [Read More...] about A New Look For 2021 From Tampa Surgical Arts

More Posts from this Category

Archives

What’s Happening

01/23/2021 – Adult craft

The Pasco County Library Cooperative will offer a virtual craft at home for adults on Jan. 23 at 2 p.m. Participants can learn to make fireworks in a jar. To view the video, visit Facebook.com/cplib. … [Read More...] about 01/23/2021 – Adult craft

01/23/2021 – Dumpling soup

The Pasco County Library Cooperative will present “Cook-a-Book: Soup” on Jan. 23 at 11 a.m. This month the book, “Dumpling Soup” by Jama Kim Rattigan will be featured. Participants can hear the story and then learn to make a kid-friendly dumpling soup. For information and to see the presentation, visit Facebook.com/regencyparklibrary. … [Read More...] about 01/23/2021 – Dumpling soup

01/23/2021 – Hobby Circle

The Pasco County Library Cooperative will offer a Hobby Circle on Jan. 23 at 3 p.m., for anyone who wants to share a hobby or learn about a new one — from a work of art to a new recipe, to a favorite video game. The group will meet via Zoom. For information, email . … [Read More...] about 01/23/2021 – Hobby Circle

01/23/2021 – Star Wars Night

The Museum of Science & Industry (MOSI), 4801 E. Fowler Ave., in Tampa, will host a Star Wars Family Night on Jan. 23 from 6 p.m. to 8 p.m., for ages 7 and older. Guests can take part in intergalactic adventures and hands-on activities, such as build-your-own lightsaber and train in the art of dueling. Participants also can control a droid through an obstacle course, learn about traveling to other planets in the Saunders planetarium, and navigate through exhibits. There also will be a game called Beat Saber on the Oculus Rift. Preregistration is required. For information and tickets, visit Mosi.org. … [Read More...] about 01/23/2021 – Star Wars Night

01/25/2021 – Fizzy bath bomb

The Land O’ Lakes Library, 2818 Collier Parkway, will offer an adult fizzy bath bomb craft, through curbside pickup only. The kit will include lavender Epsom salt, citric acid, a reusable mold, instructions and more. Pickup is from Jan. 25 through Jan. 30. Registration is required through the calendar feature on the library’s website, or by calling 813-929-1214. … [Read More...] about 01/25/2021 – Fizzy bath bomb

01/25/2021 – Lego building

Mr. John from Bricks 4 Kidz will show participants how to become a Lego Master Builder with an online class that teaches various building methods and techniques. The program will be presented on Jan. 25 at 4:30 p.m., for ages 5 to 12. Registration is through the calendar feature at HCPLC.org. … [Read More...] about 01/25/2021 – Lego building

More of What's Happening

Follow us on Twitter

The Laker/Lutz NewsFollow

The Laker/Lutz News
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
1h

Vaccine demand continues to outpace supply. https://buff.ly/3qGblWM

Reply on Twitter 1352622730059902978Retweet on Twitter 1352622730059902978Like on Twitter 1352622730059902978Twitter 1352622730059902978
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
23h

400 apartments proposed on Wesley Chapel Boulevard. https://buff.ly/38IxVb6

Reply on Twitter 1352299929759326208Retweet on Twitter 1352299929759326208Like on Twitter 1352299929759326208Twitter 1352299929759326208
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
20 Jan

"It’s Not Wednesday Until You Read The Laker!" This week's papers are out in print & online https://buff.ly/2UTt6EA

Reply on Twitter 1351958106473959428Retweet on Twitter 1351958106473959428Like on Twitter 1351958106473959428Twitter 1351958106473959428
Load More...

 

 

Where to pick up The Laker and Lutz News

Top Stories

NAMI/Pasco addresses growing need for its services

Pasco commissioners clash on apartment request

Burgess discusses pandemic response

Vaccine demand continues to outpace supply

Input from law enforcement welcome in planning efforts

Zephyrhills CRA has full plate to start new year

City of Zephyrhills gives employee service awards

Pasco allocates funds for new central office design

Don’t forget: This year’s Kumquat Festival is set for March 27

Hillsborough County’s Sunshine Line helps seniors get around

The Big Shred IV helps people dispose of documents

Pasco’s building boom creates a backlog in permits

Enjoying entertainment, and sampling syrup

Secondary Sidebar

More Stories

Check out our other stories for the week

NAMI/Pasco addresses growing need for its services

Pasco commissioners clash on apartment request

Burgess discusses pandemic response

Vaccine demand continues to outpace supply

Input from law enforcement welcome in planning efforts

Zephyrhills CRA has full plate to start new year

City of Zephyrhills gives employee service awards

Pasco allocates funds for new central office design

Don’t forget: This year’s Kumquat Festival is set for March 27

Hillsborough County’s Sunshine Line helps seniors get around

The Big Shred IV helps people dispose of documents

Pasco’s building boom creates a backlog in permits

Enjoying entertainment, and sampling syrup

Sports Stories

All-Pasco County girls fall awards announced

Banner soccer season

Local runner claims national title

Pasco County athletes compete in 2020 Florida Senior Games

South Pasco cheer program wins national titles

Copyright © 2021 Community News Publications Inc.

   