• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • About Us
  • Videos
    • Featured Video
    • Foodie Friday
    • Monthly ReCap
  • Online E-Editions
    • This Week’s E-Editions
    • 2022
    • 2021
    • 2020
    • 2019
    • 2018
    • 2017
    • 2016
    • 2015
    • 2014
  • Social Media
    • Facebook
    • Twitter
    • Instagram
  • Advertising
  • Local Jobs
  • Puzzles & Games
  • Circulation Request

The Laker/Lutz News

  • Home
  • News
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills/East Pasco
    • Business Digest
    • Senior Parks
    • Nature Notes
    • Featured Stories
    • Photos of the Week
    • Reasons To Smile
  • Sports
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills and East Pasco
    • Check This Out
  • Education
  • Pets/Wildlife
  • Health
    • Health Events
    • Health News
  • What’s Happening
  • Sponsored Content
    • Closer Look
  • Homes
  • Obits
  • Public Notices

Superior Construction

State Road 54 work expected to resume this month

December 14, 2021 By B.C. Manion

Work on a project to widen State Road 54 — from Curley Road to Morris Bridge Road — is expected to resume on Dec. 20, according to Florida Department of Transportation (FDOT) District Seven Secretary David Gwynn.

Gwynn recently updated the board of the Pasco Metropolitan Planning Organization regarding the status of three construction projects that were stalled this summer, when the contractor handling the work defaulted.

“It was the end of July when DAB  (Contractors) defaulted, more or less put us on notice that they were not financially able to continue to complete the projects,” Gwynn said.

The FDOT notified the surety, which provides the bond on the project, that is responsible for bringing in a replacement contractor to complete the work.

It typically takes two to four months to bring a replacement contractor on board, Gwynn said.

In addition to the State Road 54 project, work also was stopped on the diverging diamond interchange project at State Road 56 and Interstate 75; and on the State Road 52 project, on State Road 52, from the Suncoast Parkway to U.S. 41, including a portion of U.S. 41.

Work has resumed on the diverging diamond project, with Superior Construction handling the job. That’s the same company that’s building the realignment of State Road 52 in East Pasco.

“They jumped onto the diverging diamond. One thing they just recently did, it wasn’t really required of them in the contract, but for the Christmas holiday season, opened up an additional lane on State Road 56 to try to help with the merchants in the area and be able to provide a little better service during the shopping season,” Gwynn said.

The contractor expects to have the new configuration completed by summer 2022, Gwynn said.

The State Road 52 project is being handled by a company called PCS (previously known as Pepper). The work has begun, but there’s still about two years left on that project, the FDOT officials said.

“The one that’s given us the most challenge has been State Road 54, for a variety of reasons,” he said.

That work will be completed by Cone & Graham, which is the company that is building the county’s Ridge Road project and that built the State Road 56 extension, Gwynn said.

Gwynn also noted there are some traffic issues at the new leg of an intersection at Meadow Pointe Boulevard and State Road 54, which has to do with an equipment issue. He said that is expected to be corrected in coming weeks.

The Pasco MPO — made up of representatives of Pasco County, Dade City, Zephyrhills, Port Richey and New Port Richey — is the lead transportation planning agency in Pasco County.

Published December 15, 2021

Crews getting back at it, on Diverging Diamond interchange

September 14, 2021 By B.C. Manion

Work on the diverging diamond project at State Road 56 and Interstate 75 in Wesley Chapel was set to resume on Sept. 13, according to officials from the Florida Department of Transportation.

That news was part of an update released by Kris Carson, department spokeswoman for FDOT’S District 7 office.

Work was halted in June, when D.A.B. Constructors notified FDOT that it was demobilizing from the project. The state transportation department then defaulted D.A.B., on July 1.

D.A.B. Contractors had seven projects in FDOT District 7, including three in Pasco County. After D.A.B. was defaulted on the diverging diamond project, it self-defaulted on the other Pasco projects, which are on State Road 52 and State Road 54.

The surety company must now complete those projects.

Carson provided a Sept. 10 update regarding the status of the projects.

Diverging Diamond
The completion contract has been executed by Superior Construction and is with the surety for final signatures.

Superior Construction has been given a Notice to Proceed from the surety, and contract work is expected to recommence on Sept. 13.

Surveyors have been onsite gathering survey information to support the proposed Sept. 13 start date.

The interim maintenance contractor (DBI) performed mowing in the two ponds on the south side of State Road 56. Slope mowing was completed on the northeast quadrant adjacent to the northbound Interstate 75 on-ramp.

Slope mowing is currently underway on the interior slopes of the southbound on- and off-ramps.

A project-wide litter pickup cycle was completed.

State Road 52, from Suncoast Parkway to U.S. 41
The surety received bids from prospective completion contractors on Sept. 9, and the bids are being evaluated.

The FDOT performed pothole and silt fence repairs, to address urgent needs.

An upcoming mowing cycle is planned to start in two weeks.

State Road 54, from Curley Road to Morris Bridge Road
The surety put out an advertisement for bids on Sept. 9, with bids expected to be received the week of Sept. 23.

The FDOT’s maintenance crews have repaired potholes throughout the project and at the following side streets and driveways: McDonald’s driveway, Lado Drive, Loury Drive, Ashton Oaks Boulevard and Foxwood Boulevard.

Drop-offs have been addressed project-wide by inspection staff and maintenance crews.

The FDOT’s asphalt maintenance contractor is schedule to pave the previously listed side streets and driveways beginning Sept. 16.

Traffic markings maintenance has been completed at Meadow Pointe Boulevard and State Road 54.

Concrete barriers were adjusted at New River Road and State Road 54 and the Morris Bridge Road intersection, in front of CVS.

Emerald Striping is being scheduled to install flashing beacon ‘school ahead’ signs at New River Academy.

While the FDOT continues to address the state road projects that are behind schedule, State Sen. Danny Burgess told members of the North Tampa Bay Chamber of Commerce that the state is seeing what it can do to streamline, in some way, the process of road contracting.

That way, if something like this happens again, the DOT would have additional options, such as going to with Bidder No. 2 on a project, he said.

“We’re going to look at some outside-the-box opportunities,” Burgess said.

Published September 15, 2021

State roads department offers update on halted Pasco projects

August 18, 2021 By B.C. Manion

Florida Department of Transportation District Seven Secretary David Gwynn recently gave an update on the status of state road projects that recently halted operations.

Gwynn gave the update during the Aug. 12 board meeting of the Pasco County Metropolitan Planning Organization.

The Pasco MPO — made up of representatives of Pasco County, Dade City, Zephyrhills, Port Richey and New Port Richey — is the lead transportation planning agency in Pasco County.

Work has stopped on a diverging diamond project that is being done in Wesley Chapel, which is expected to ease traffic at State Road 56 and Interstate 75, once the work is finished. An estimated completion date on the project has not been determined. (File)

Gwynn told the MPO board members: “We had seven projects in our district, three of them in Pasco County, that DAB Contractors either were defaulted on — which was the DDI (Diverging Diamond Interchange) — or self-defaulted, which included State Road 52 and State Road 54.

“After that occurred, we met with our surety company — more or less the bondholder.

“I can tell you the surety has been very responsive so far,” he said.

He expressed confidence that once the surety company awards a bid on the contract, the contractor will “try to get this project not only going, but accelerating as quickly as possible.”

Gwynn also noted: “We’re also working with our maintenance contractor to ensure that the project sites are secured. I’ve noticed recently that some of the vegetation in some of the areas is starting to grow pretty high, so we’re out there with our forces, mowing them. In fact, we’re doing (State Road) 54, I think, today.

“The surety has let me know the direction they’ve given their people is that they need to get these contracts going as soon as possible because they’re also held to the same penalties as DAB would have been held to for being late. In other words, the end date of the contract doesn’t change. They’ll get penalized for every day they don’t meet, based on that original contract.

“I’m very optimistic that very soon we’ll have contractors on board working on those projects.

“When you look at some of the other construction projects we have around in Pasco County and around the district, a lot of the contractors are ahead of schedule. The State Road 52 realignment project is almost a year ahead of schedule, with Superior Construction.

“The Overpass Road Interchange is ahead of construction, so I think there’s capacity out there to get other good contractors and get these jobs moving forward.”

Kris Carson, spokeswoman for the FDOT District Seven Office, provided an Aug. 13 update regarding the status of the projects.

The surety company and the FDOT have executed a takeover agreement regarding the diverging diamond project, as of Aug. 12, according to Carson’s update.

The receipt of bids for the project had been scheduled for Aug. 12, but was moved back to Aug. 18, to provide more information and give more contractors an opportunity to compete for the work.

Mowing and general maintenance has been completed throughout the project limits.

Also, the number of temporary traffic control devices have been reduced to the minimum required to maintain a safe work zone, the update adds.

Regarding the State Road 52 project, from Suncoast Parkway to U.S. 41: A representative with the surety met with an FDOT representative onside to assess the status of the project, on Aug. 11. The FDOT has completed uploading all of the documentation requested by the surety and the takeover documents are with the surety, for its execution.

Regarding the widening of State Road 54, from Curley Road to Morris Bridge Road: A representative with the surety met with a FDOT representative onsite to assess the status of the project, on Aug. 11. The FDOT has completed uploading all of the project documentation requested by the surety. The takeover documents are currently with the surety for its execution.

The FDOT has completed mowing throughout the project area. Additional maintenance of driveway access to business on the west side of Eiland/State Road 54 is planned to be completed within the next two weeks, according to the Aug. 13 update.

The surety will be responsible for meeting the original contract requirements, and the FDOT retains the responsibility to ensure the surety meets its obligations, the FDOT document adds.

Published August 18, 2021

Primary Sidebar

A Conversation with Lutz Filmmaker, Alexis Yahre

Search

Sponsored Content

A Guide for Summer Camps in Pasco County 

May 23, 2022 By Special to The Laker/Lutz News

Summer break is quickly approaching and organizations throughout Pasco County are offering camps for children of all … [Read More...] about A Guide for Summer Camps in Pasco County 

Avalon Applauds Kids Helping Kids Pasco County 

May 10, 2022 By Special to The Laker/Lutz News

Congratulations to Kids Helping Kids Pasco County for being applauded by Avalon Park Wesley Chapel. The nonprofit … [Read More...] about Avalon Applauds Kids Helping Kids Pasco County 

More Posts from this Category

What’s Happening

05/26/2022 – Food distribution

Farm Share, the Pasco Sheriff’s Office, Pasco Sheriff Charities, the Pasco County NAACP, and the Boys & Girls Clubs of Tampa Bay will partner for a free food distribution on May 26 starting at 9 a.m., at the Boys & Girls Club of Lacoochee, 38724 Mudcat Grant Blvd., in Dade City. Food will be given out on a first-come, first-served basis, while supplies last. The event is a drive-thru, rain or shine. … [Read More...] about 05/26/2022 – Food distribution

05/28/2022 – Memorial Day Concert

The “Let’s Do Good Memorial Day Concert” is scheduled for May 28 from 1 p.m. to 7 p.m., at Land O’ Lakes Heritage Park, 5401 Land O’ Lakes Blvd., to benefit the Tunnel to Towers Foundation. Tunnel to Towers provides mortgage-free homes to Gold Star and fallen first responder families with young children, and builds custom-designed smart homes for catastrophically injured veterans and first responders. The foundation is committed to eradicating veteran homelessness and aiding the victims of major U.S. disasters. The event will include vendors, gifts, a Forget-Me-Not Garden, and more. Entertainment will be provided by Fred Chandler, Charles Goodwin, Cruz Er Mac, Mike Henderson, and Travis White. Special guests include Congressman Gus Bilirakis and State Sen. Danny Burgess. Rain date is Sept. 10. … [Read More...] about 05/28/2022 – Memorial Day Concert

05/28/2022 – Seafood Festival-CANCELLED

The North Tampa Bay Chamber’s Summer Seafood Festival is scheduled for May 28 from 11 a.m. to 7 p.m., at the Tampa Premium Outlets, 2300 Grand Cypress Drive in Lutz, between the outlets and At Home. There will be seafood, crab races, a kids zone, live bands, craft beer, a local market, a Nautical Art Show, and a crab claw-eating contest. For information, call 727-674-1464. … [Read More...] about 05/28/2022 – Seafood Festival-CANCELLED

06/04/2022 – D-Day reenactment

The Zephyrhills Museum of Military History, 39444 South Ave., in Zephyrhills, will present “D-Day, Invasion of Normandy” on June 4 from 10 a.m. to 4 p.m. There will be an opening ceremony at 11 a.m. The event will include skydivers, reenactors, World War II veterans, and WWII vehicles/aircraft on display. Visit zmmh.org/events, for additional information. … [Read More...] about 06/04/2022 – D-Day reenactment

06/11/2022 – Community cleanup

Save the date: A Dade City Community Cleanup is scheduled for June 11 from 8 a.m. to noon. The city will provide two garbage trucks and one roll-off to dispose of household waste. Residents will be able to drop off unwanted items at three locations. Volunteers also are needed and can register online at DadeCityFl.com. More information will be forthcoming. … [Read More...] about 06/11/2022 – Community cleanup

06/13/2022 – Vacation Bible School

The Church at Myrtle Lake, 2017 Riegler Road in Land O’ Lakes, will host the Spark Studios Vacation Bible School from June 13 to June 17 from 9 a.m. to noon. The event is free for children of age who have completed kindergarten through sixth grade. Registration is open online at MyrtleLake.org. For information, call 813-949-5516. … [Read More...] about 06/13/2022 – Vacation Bible School

More of What's Happening

Follow us on Twitter

The Laker/Lutz NewsFollow

Home for all your local news in Land O' Lakes, Lutz, New Tampa, Wesley Chapel, Zephyrhills and Dade City.

The Laker/Lutz News
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
22 May

SUNDAY MORNING SPORTS: Wyatt Deaton, 11, of Wesley Chapel, swam 2 miles and raised $5,900 for charity at the Swim Across America fundraising event. Great picture @MikeCamunas! Full story ---> https://buff.ly/3lktCIv

Reply on Twitter 1528367595258265600Retweet on Twitter 15283675952582656001Like on Twitter 15283675952582656001Twitter 1528367595258265600
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
21 May

Go Pasco — Pasco County’s public bus service — is planning to use technology to enable riders to get up-to-date information to track buses in real time https://buff.ly/3aafXS6

Reply on Twitter 1528073180073574404Retweet on Twitter 1528073180073574404Like on Twitter 15280731800735744042Twitter 1528073180073574404
LakerLutzNewsThe Laker/Lutz News@LakerLutzNews·
21 May

What an AMAZING transformation! 💫 The Block is housed in a historic building that was an auto dealership in the 1920s. Now, its a venue space, a brewhouse, a restaurant, a CrossFit gym and more ---> https://buff.ly/3PsLvTo

3
Reply on Twitter 1528027975391772673Retweet on Twitter 15280279753917726731Like on Twitter 15280279753917726731Twitter 1528027975391772673
Load More...

Archives

 

 

Where to pick up The Laker and Lutz News

Copyright © 2022 Community News Publications Inc.

    Doc