• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • About Us
  • Videos
    • Featured Video
    • Foodie Friday
    • Monthly ReCap
  • Online E-Editions
    • 2025
    • 2024
    • 2023
    • 2022
    • 2021
    • 2020
    • 2019
    • 2018
    • 2017
    • 2016
    • 2015
    • 2014
  • Social Media
    • Facebook
    • Twitter
    • Instagram
  • Advertising
  • Local Jobs
  • Puzzles & Games
  • Circulation Request

The Laker/Lutz News

Serving Pasco since 1981/Serving Lutz since 1964

  • Home
  • News
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills/East Pasco
    • Business Digest
    • Senior Parks
    • Nature Notes
    • Featured Stories
    • Photos of the Week
    • Reasons To Smile
  • Sports
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills and East Pasco
    • Check This Out
  • Education
  • Pets/Wildlife
  • Health
    • Health Events
    • Health News
  • What’s Happening
  • Sponsored Content
    • Closer Look
  • Homes
  • Obits
  • Public Notices
    • Browse Notices
    • Place Notices

State road projects in Pasco approach $290 million

May 11, 2021 By B.C. Manion

During a recent transportation Zoom briefing with the North Tampa Bay Chamber of Commerce, Kevin Thibault, secretary of the Florida Department of Transportation, provided an overview of projects that are in various stages of progress in Pasco County.

Here’s a recap of information from his PowerPoint presentation and of his comments, project by project.

(Courtesy of Florida Department of Transportation)

Diverging Diamond, at State Road 56
Project description: Converts from a standard diamond interchange to a diverging diamond interchange

  • Ongoing work is occurring on all four quadrants of the interchange.
  • The traffic pattern shift will occur this fall.
  • Project cost: $33 million

Estimated completion: Late 2021

Thibault’s comments: “The DDI (Diverging Diamond Interchange) was chosen for this interchange to increase safety and capacity, through an increased number of lanes; improving pedestrian facilities; more efficient signal timings; and, reducing vehicle conflicts.

“Work is occurring on all four quadrants, rebuilding the interchange ramps.

“Work is taking place in the median of the existing State Road 56 bridge over Interstate 75.

“Various traffic shifts are taking place and will continue to take place on State Road 56, on both sides of Interstate 75, as the contractor builds the improvements necessary to make the conversion to the diverging diamond configuration.

“Traffic is anticipated to be switched to the new diverging diamond pattern in the fall of 2021.

“The current estimated completion date is later this year.

“As many of you know, this project has overcome some errors and periods of insufficient resources by the contracting team, but milestones have been met related to the project completion, to ensure that sufficient progress is being made.

“The department understands that this is an important corridor in Pasco County and will continue our efforts to guide the contractor to complete the project, as quickly as possible.”

State Road 54 widening, from Curley Road to Morris Bridge Road
Project description: State Road 54 is being widened from two lanes to four lanes, with a median

  • Project cost: $42.5 million
  • Estimated completion: Late 2021

Thibault’s comments: “Widening of State Road 54, as shown here in this aerial from Curley Road to Morris Bridge Road, will widen the roadway from two lanes to a four-lane highway, with a median. Long stretches of new roadway are currently in use, with bi-directional traffic shifting either to the future eastbound or westbound pavement. Drainage, roadway and utility construction continues throughout the project area.

“Additional traffic switches will be coming, as new roadway segments are completed.

“In addition, a sidewalk will be built on the north side of the road, and a 10-foot-wide, multi-use trail will be built on the south side.”

New Interstate-75 interchange at Overpass Road
Project description: Existing bridge at Overpass Road was removed. Construction has begun on a new bridge.

  • Overpass Road will be widened from two lanes to four lanes, between Interstate 75 and Old Pasco Road. It will be widened to six lanes, from I-75 to Boyette Road.
  • Project cost: $64 million for this design-build project
  • Estimated completion: November 2022

Thibault’s comments: “This design-build project is to construct a new interchange approximately 3 ½ miles, south of State Road 52 in Pasco County.

“Overpass Road is closed, between Boyette and Old Pasco roads. It’s scheduled to reopen in February of 2022.

“Blair Drive has been realigned to connect with Old Pasco Road. McKendry Road has been realigned to connect with Boyette.

“The entrance to Wesley Chapel District Park from Overpass Road has been permanently closed.

“The entrance ramp construction has begun on all four quadrants.

“The project is progressing well.

“The new diamond interchange will include a flyover ramp for westbound Overpass Road access onto southbound I-75.

State Road 52, near U.S. 41
Project description: Widening of State Road 52, from the Suncoast Parkway to east of U.S. 41.

Widening State Road 52 to a six-lane divided highway; includes the widening of U.S. 41 approaching State Road 52, in each direction

  • Project also consists of building stormwater ponds, installing drainage pipes, building roadway base and relocating utilities.
  • Project cost: $49.7 million

Thibault’s comments:  “This is close to a $50 million project and the estimated completion is February of 2023, which is currently ahead of schedule that’s posted on the project website.”

U.S. 41, north of Connerton
Project description: Widening of U.S. 41, from north of Connerton to State Road 52, widens U.S. 41 into a four-lane divided highway

  • Project cost: $16.8 million
  • Estimated completion: February 2023

Thibault’s comments: “The project clearing is almost completed.

“Utility relocation and erosion control measures are underway.

“The drainage and excavation activities are set to begin shortly.

“Again, currently ahead of the schedule posted on the project website.”

Widening and new alignment of State Road 52
Project description:
Widens State Road 52 to a four-lane divided highway and realigns the corridor from Uradco Place to west of Fort King Road

  • Miles of new roadway have been constructed.
  • A lane reduction recently has been put in place along eastbound State Road 52, from I-75 to allow for construction at the west end of the project.
  • Project cost: $81.4 million
  • Estimated completion: August 2023

Thibault’s comments: “It is progressing well and is slightly ahead of schedule.”

Published May 12, 2021

Share this:

  • Tweet
  • Click to share on Reddit (Opens in new window) Reddit
  • Share on Tumblr
  • Click to email a link to a friend (Opens in new window) Email
  • Click to print (Opens in new window) Print

Like this:

Like Loading...

Reader Interactions

Comments

  1. David Towns says

    May 17, 2021 at 6:16 pm

    Just opening up Pasco for more traffic and building. Getting over crowded.

    Log in to Reply

Leave a Reply Cancel reply

You must be logged in to post a comment.

Primary Sidebar

Search

Sponsored Content

All-in-one dental implant center

June 3, 2024 By advert

  … [Read More...] about All-in-one dental implant center

WAVE Wellness Center — Tampa Bay’s Most Advanced Upper Cervical Spinal Care

April 8, 2024 By Mary Rathman

Tampa Bay welcomes WAVE Wellness Center, a state-of-the-art spinal care clinic founded by Dr. Ryan LaChance. WAVE … [Read More...] about WAVE Wellness Center — Tampa Bay’s Most Advanced Upper Cervical Spinal Care

More Posts from this Category

Archives

 

 

Where to pick up The Laker and Lutz News

Copyright © 2025 Community News Publications Inc.

   
%d