Stormwater drainage improvements are coming to the intersection of 15th Street and Main Avenue in Dade City — an area officials say has been long plagued by flooding problems.
The intersection runs between Cox Elementary School and Watson Park. It also is near the future site of The Cove, a 10-unit Habitat for Humanity residential development.
Dade City Commissioners on March 9 voted unanimously to award the construction project to Tampa-based Kamminga & Roodvoets Inc. The company’s bid of $94,753 was the lowest of four submitted. Others came in at $122,460.25, $125,750 and $147,130.
The project scope calls for installing curb inlets and storm pipe at the intersection; constructing concrete curb; installing pavement and an asphalt wing; installing a ditch bottom inlet and constructing ditch pavement to match the street’s existing ditch grade, among other improvements. The contractor has 100 calendar days to achieve substantial completion.
The project was originally budgeted for $95,000, from the Penny for Pasco local government infrastructure surtax fund.
The city, in 2019, obtained engineering design services of Wood Environmental and Infrastructure Inc., to prepare bid-ready construction drawings for the drainage improvements. The engineer’s cost estimate at the time was $89,120.
Mayor Camille Hernandez described the project as “long-needed” and “overdue.”
“I’m very pleased to see this and happy that we awarded that (bid),” Hernandez said. “The folks (in the neighborhood) we have met at different times and stages are looking forward to that, and there’s a lot of development happening with The Cove and other things.”
Kamminga & Roodvoets also was the contractor on the city’s recent multimillion downtown stormwater piping system spanning Seventh Street, Pasco Avenue, Third Street, Meridian Avenue and other areas.
Published March 24, 2021
Leave a Reply
You must be logged in to post a comment.