Pasco County continues to lay the groundwork for overpasses on the Suncoast Parkway, at State Road 52 and at State Road 54.
The Pasco County Commission on May 3 adopted an amendment to a Locally Funded Agreement between the county and the Florida Department of Transportation (FDOT) for the planned bicycle/pedestrian overpass at Suncoast Trail, over State Road 52.
Board members approved the amendment for $216,447, as part of the board’s consent agenda — meaning it was approved as part of a bundle of items, without discussion.
At its Feb. 3 meeting, the board approved a lump sum for the design and construction of the overpass, and the agreement calls for FDOT to be responsible for preparing the design plans, advertising, and letting the construction contract, to include utility coordination, permitting and the Construction Engineering Inspection for the project.
In the agreement, the county is responsible for the completion of all required survey, geotechnical exploration, and Subsurface Utility Engineering (SUE).
Since then, it has been decided that the FDOT would be responsible for completing the work the county was going to do, since FDOT already has consultants in place to perform the necessary work.
The total estimated project cost is slightly under $10 million, which the county has provided.
It now will furnish the additional funds, by May 27, for geotechnical exploration, Subsurface Utility Engineering (SUE) and survey activities associated with this project.
The design, including geotechnical work, is slated to begin this year and be completed by 2023, Construction is scheduled to be completed in 2024.
In another action, the county board approved amending an agreement with the FDOT for work associated with the planned overpass at State Road 54 and the Suncoast Trail. That agreement increased the county’s contribution by $190,007.
That action also was on the board’s consent agenda.
Like the work for the other overpass, this agreement covers expenses for work that FDOT will now do, instead of the county, relating to geotechnical exploration, Subsurface Utility Engineering (SUE) and survey activities associated with this project.
The design work on the State Road 54 overpass is expected to be completed in 2023 and the construction is expected to be completed in 2024.
Published May 11, 2022