• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • About Us
  • Videos
    • Featured Video
    • Foodie Friday
    • Monthly ReCap
  • Online E-Editions
    • 2025
    • 2024
    • 2023
    • 2022
    • 2021
    • 2020
    • 2019
    • 2018
    • 2017
    • 2016
    • 2015
    • 2014
  • Social Media
    • Facebook
    • Twitter
    • Instagram
  • Advertising
  • Local Jobs
  • Puzzles & Games
  • Circulation Request

The Laker/Lutz News

Serving Pasco since 1981/Serving Lutz since 1964

  • Home
  • News
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills/East Pasco
    • Business Digest
    • Senior Parks
    • Nature Notes
    • Featured Stories
    • Photos of the Week
    • Reasons To Smile
  • Sports
    • Land O’ Lakes
    • Lutz
    • Wesley Chapel/New Tampa
    • Zephyrhills and East Pasco
    • Check This Out
  • Education
  • Pets/Wildlife
  • Health
    • Health Events
    • Health News
  • What’s Happening
  • Sponsored Content
    • Closer Look
  • Homes
  • Obits
  • Public Notices
    • Browse Notices
    • Place Notices

Work resumes on State Road 52 widening

November 9, 2021 By B.C. Manion

Construction has restarted on State Road 52, near the Suncoast Parkway, in Land O’ Lakes.

A new contractor, PCS Civil Inc., began work on Oct. 25.

The contractor is expected to spend a few weeks doing cleanup, surveying and other tasks necessary to safely resume operations, according to an update from the Florida Department of Transportation’s (FDOT) District Seven office.

Work on the project stopped on July 28, 2021, when the original contractor notified FDOT that it was halting work on the project. The state transportation department declared the contractor in default on Aug. 3.

Pipes await a crew on the south side right of way, along State Road 56. Construction again has started up on a project aimed at easing congestion at the State Road 56 and Interstate 75 interchange, in Wesley Chapel. (File)

The FDOT requires its contracts to have bonds issued by a surety company.

The surety company was required to obtain a completion contractor and chose PCS Civil Inc.

The State Road 52 project calls for widening the road to a six-lane divided highway from the Suncoast Parkway to east of U.S. 41.

The contract also includes widening U.S. 41 for approximately 1 mile, approaching the State Road 52 intersection. A 12-foot wide multi-use trail — to be built along the north side of State Road 52 — is another element of the project.

The estimated cost for the State Road 52 widening is $49.8 million, according to FDOT’s website.

While work has resumed on State Road 52, it is expected to begin again soon on the State Road 54 widening, from Curley Road to Morris Bridge Road, according to the FDOT update.

The prospective completion contractor is sending the surety company an updated price proposal.

A completion contract is expected to be with the surety by Nov. 12, with execution of the contract to follow. Once that occurs, the contractor is expected to begin work within a week.

In the meantime, mowing and litter removal is expected to occur.

Another project that had been halted involves the construction of the Diverging Diamond Interchange (DDI) project being built at the State Road 56 and Interstate 75 interchange.

That work stopped June 25, when the contractor informed FDOT it was halting work on the project. On July 1, FDOT declared the contractor in default.

Work resumed on Sept. 13, after Superior Construction Company Southeast LLC was selected by the surety company to complete the work.

The project, estimated at $33.6 million, is now expected to finished in summer 2022, according to FDOT’s website.

The project will reconfigure the State Road 56/I-75 interchange between County Road 54 and Cypress Ridge Boulevard.

The existing diamond interchange at the intersection will be converted to a DDI.

The main change will be to diverge, or cross, State Road 56 traffic to the left side of the road through the interchange, and then cross vehicles back over to the right side of the road on the opposite side of the interchange, according to a description on FDOT’s website.

The changes will help to alleviate traffic congestion to reduce travel time for motorists in this rapidly growing area.

A DDI was chosen for the State Road 56/I-75 interchange because of the proven ability of this traffic configuration to increase safety and capacity while using a large amount of the existing interchange footprint, including the existing bridge, according to FDOT.

The DDI also was chosen because of its ability to handle heavy left-turn volumes, such as the westbound to southbound movement from State Road 56 to southbound I-75.

For more information about these or other FDOT projects in Pasco or Hillsborough counties, visit FDOTtampabay.com.

Published November 10, 2021

Share this:

  • Tweet
  • Click to share on Reddit (Opens in new window) Reddit
  • Share on Tumblr
  • Click to email a link to a friend (Opens in new window) Email
  • Click to print (Opens in new window) Print

Like this:

Like Loading...

Reader Interactions

Leave a Reply Cancel reply

You must be logged in to post a comment.

Primary Sidebar

Search

Sponsored Content

All-in-one dental implant center

June 3, 2024 By advert

  … [Read More...] about All-in-one dental implant center

WAVE Wellness Center — Tampa Bay’s Most Advanced Upper Cervical Spinal Care

April 8, 2024 By Mary Rathman

Tampa Bay welcomes WAVE Wellness Center, a state-of-the-art spinal care clinic founded by Dr. Ryan LaChance. WAVE … [Read More...] about WAVE Wellness Center — Tampa Bay’s Most Advanced Upper Cervical Spinal Care

More Posts from this Category

Archives

 

 

Where to pick up The Laker and Lutz News

Copyright © 2025 Community News Publications Inc.

   
%d